GAZETTE NOTICE NO. 13176
GAZETTE NOTICE NO. 13176
THE WATER ACT
(Cap. 372)
CORRIGENDUM
Whereas Gazette Notice No. 12825 of October 2024, published the water and sanitation tariffs for Eldoret Water and Sanitation Company
(ELDOWAS);
And whereas, upon further review and consideration of the parties’ consent to an arbitration at the Water Tribunal under Appeal Case No. E006
Of 2025, it has been determined that the tariffs need to be revised downwards;
Now, therefore, pursuant to section 72 (1) (b) and (2) of the Water Act, 2016, the Water Services Regulatory Board revokes the tariff structure published in the Gazette Notice No. 12825 of 2024.
Consequently, it is hereby notified that the revised water and sanitation tariffs for ELDOWAS for the remaining period of 2026/2027 to
2028/2029 shall be as follows:
1.0 Approved Tariff Structure
1.1 Water Tariff Structure for the period 2026/2027 to 2028/2029
14th August, 2026 THE KENYA GAZETTE
Consumer Categories Consumption Block (m3) Approved Tariff (KSh./m3)
Domestic/Residential 1-6 84
7-20 95
21-50 110
51-100 117
101-300 128
>300 140
Multi-Dwelling Units Per M3 96
Commercial/Industrial 1-50 108
51-100 115
101-300 130
>300 140
Government/Institutions 1-50 108
51-100 115
101-300 130
>300 140
Public Schools, Colleges, and
Universities
1-600 88
601-1200 97
>1200m3 109
Unique Consumer Categories Bulk Water Supply Per m3 60
Water Kiosks Per m3 88
Customers with non-functional meters shall be billed based on the average of the last three months’ bills.
1.3 Sewerage Tariff Structure for the period 2026/2027 to 2028/2029.
1.3.1 Consumers with a Water Connection
(c) Sewerage will be charged at 75% of the water volumes, billed at the rates specified below for all customer categories.
Consumer Categories Consumption Block (m3) Approved Tariff (KSh. /m3)
Domestic/Residential 1-6 63
7-20 72
21-50 83
51-100 88
101-300 100
>300 110
Multi-Dwelling Units Per M3 72
Commercial/Industrial 1-50 83
51-100 88
101-300 100
>300 110
Government/Institutions 1-50 83
51-100 88
101-300 100
>300 110
Public Schools, Colleges, and
Universities
1-600 70
601-1200 85
>1200m3 100
(d) Disconnected water accounts shall be charged on the average of the last three months’ sewerage charges before disconnection
1.2.2 Consumers without a water connection
Sewerage consumers without a water connection shall be charged as follows:
(a) Single dwelling domestic unit: KSh. 300 per month.
(b) All other categories :75% of the volume of water consumed as per the metered source of water at the rates specified (in 1.2.1(a)) above.
1.3 Indexation
The utility’s approved tariffs for water and sewerage shall be eligible for annual indexation, as per the regulations of the Water Services
Regulatory Board (WASREB). The inflation adjustment shall come into effect every July of the tariff period commencing July 2027.
1.4 Miscellaneous Charges
These shall be as follows:
Item/ Service Charge (KSh.)
Water Deposit
Category of consumer
Domestic 2500
Retail shops less than 10m3 3000
Retail shops with more than 10m3 3,500
Bar and restaurants with less than 15 m3 4000
Bar and restaurants more than 15 m3 6,000
Hotel class “A” and “B” with less than 150 m3 12,000
Hotel class “A” and “B” with more than 150 m3 15000
Hotel class “C” and ‘D’ less than 150 m3 18000
3982 3982
Item/ Service Charge (KSh.)
Hotel class “C” and ‘D’ more than 150 m3 20,000
Hospitals and Health centres with more than 150 m3 20,000
Hospitals and Health centres with less than 150 m3 12,000
Schools and other institutions have more than 200 m3 20,000
Schools and other institutions with less than 200 m3 10,000
Minor construction sites of more than 200 m3 15,000
Major construction sites with more than 300 m3 50,000
Light industries with less than 200 m3 30,000
Medium industries between 200 m3 and 300 m3 50,000
Heavy industries of more than 300 m3 100,000
Water Kiosks 5,000
Customers with only a sewer connection are to be charged a deposit equivalent to a water connection
Other Charges
Service
New water connection fee – Connection size: ½ inch to 1 inch 2,500
New water connection fee – Connection size: 1.5 inches to 3 inches 7,500
New water connection fee – Connection size above 3inches 15,000
Water Reconnection fee – at meter point 1,000
Water Reconnection fee – at mains 5,000 and double deposit
Tanker – 7000 and 18,000 litres 2,500 and 6,000 respectively per tanker within ELDOWAS area for all consumers
Sale of water per M3 at Browsing Point (own tanker) 107
Replacement of stolen or damaged meters 100% of the market cost of the meter
Meter testing on request 500
Sewer Connection- Residential/ Domestic 5,000
Sewer Connection- Commercial, Government, Schools, Universities, and
Colleges
7,500
Sewer Connection- Industrial 15,000
Private sewer unblocking 2,500
Leak detection services 1,000
Sewer Reconnection fee 15,000
Printing of the customer’s statement on their own request 200
For cutting off the supply at the request of the consumer 200
For turning on the supply otherwise than in respect of a first connection 200
Exhauster Services (Company Exhauster) 5,000 for other customers and 4,000 for informal settlements
Private Exhausters (Dumping into the company’s sewer system) 6,500 per Truck per month
Penalties
Illegal water connection -Commercial, Industry, Construction (Fraud) 100,000 plus estimated consumption during the period of illegality
Illegal water connection (Fraud) – Domestic 30,000 plus estimated consumption during the period of the illegality
Overcharging (fraud) at the water kiosk 15,000
Illegal sewer connection- Commercial, Industry, Construction 100,000
Illegal sewer connection- Domestic, Government, Schools, Universities &
Colleges
30,000
Self-reconnection after cut-off for non-payment 5,000, and billing to be backdated from the date of the cut-off
Surcharge for tampering with meters (this includes meter removal, reversing of meter, etc.)
5,000
Surcharge for direct suction of water from the supply line using a pump 10,000
2.0 Cost Structure
2.1 Cost Summary
Below is the summary of the projected annual cost structure that makes up the total costs to be incurred by ELDOWAS during the tariff period:
Expenditure Item 2025/26 2026/27 2027/28 2028/29
Operations 772,912,996 789,605,791 833,396,909 877,688,438
Maintenance 51,376,681 76,350,000 77,175,000 79,795,000
Regulatory Levy 50,593,223 52,671,254 53,986,488 55,302,879
Total O&M Costs 874,882,900 918,627,045 964,558,397 1,012,786,317
Investment Costs 59,233,971 190,121,196 189,518,820 196,707,598
Debt Repayment 69,761,819 69,574,626 78,989,005 77,748,590
Total Costs 1,003,878,689 1,178,322,867 1,233,066,223 1,287,242,505
Total Billing (KSh) 1,264,830,577 1,267,718,958 1,300,599,828 1,333,509,589
Collection Efficiency (%) 94% 95% 95% 95%
Projected Revenue 1,188,940,742 1,204,333,011 1,235,569,837 1,266,834,110
O&M Cost Coverage 136% 131% 128% 125%
Total Cost Coverage 118% 102% 100% 98%
4.0 Conditions attached to the tariff approval.
14th August, 2026 THE KENYA GAZETTE
The conditions attached to this approval, which shall form part of the license conditions of ELDOWAS, are:
4.1 Service Delivery Conditions attached to the Tariff
Target 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029
Water Coverage (%) 84% 84% 85% 85% 86%
Sewerage Coverage (%) 40% 43% 46% 49% 52%
Water quality standards (%) 96% 100% Compliance with Standards
Personnel Expenditure as % of O&M 51% 51% 45% 42% 40%
Non-Revenue Water 44% 39% 36% 35% 34%
Hours of Supply (Hrs.) 23 23 23 23 24
Staff per 1000 connections 4 4 4 4 4
Metering ratio (%) 100% 100% 100% 100% 100%
Collection Efficiency (%) 91% 95% 95% 95% 95%
Resale at Kiosk KSh. 3.00 per 20L Jerry Can
4.2 Annual budgets: The WSP shall adhere to the budgetary levels set in the tariff.
4.3 Surpluses: The surpluses realised during the tariff period shall be used to implement priority service delivery capital projects approved by
WASREB
4.4 Reporting: The utility shall submit to WASREB a quarterly performance report in the format provided.
4.5 Creation of distinct water and sewer cost centres: ELDOWAS will ensure that separate water and sewer cost centres are created and that different records of operations of the two centres are maintained
4.6 Catchment Protection: The utility shall undertake measures to conserve/ protect the catchment areas of their source of water as part of
Corporate Social Responsibility
4.7 Regulatory Levy: The utility is to pay a monthly regulatory levy based on 4% of turnover, which is inclusive of billing for other services and interest income earned.
4.8 Investments: The utility shall undertake the investments in Appendix 1
The utility shall undertake the following investments within the tariff period:
Item 2026/2027 2027/2028 2028/2029
Annual Budget (KSh) 190,121,196 189,518,820 196,707,598
4. Penalty notice
4.1 Take note that failure of an Accounting Officer to administer this tariff and the conditions attached to it is an offence subject to section 196
(2) of the Public Finance Management Act 2012, 117 (1) (aa) of the County Governments Act 2012, Sections 147 and 158 of the Water Act
2016, and Regulations 46 (1), 101 and 105 of the Water Services Regulations 2025.
4.2 Failure to comply with the tariff and conditions attached to it amounts to a breach of licence conditions and shall attract sanctions pursuant to section 92 of the Water Act 2016, including:
(i) Payment of a penalty
(ii) Suspension or cancellation of the licence.
(iii) Placement of the utility under Special Regulatory Regime.
(iv) Prosecution.
Appendix 1: Investments through internally generated funds by Eldoret Water and Sanitation Company LTD
Project 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029
1.0 Asset Renewal
1.1 Sosiani Treatment Replacement of Sosiani 300L air compressor
- 600,000
Replacement of Sosiani water collection troughs
- 5,000,000
1.2 Quarry Treatment Replacement of AQ range valve actuators
6,000,000
Quarry 14kW submersible recirculation pumps
9,000,000
Quarry 33kW submersible waste water pumps
12,000,000
Quarry waste collection auto manual step screen
15,000,000
1.3 Lab Equipment Replacement of various water and waste water testing equipments
2,500,000 2,500,000 2,500,000 2,500,000 2,500,000
1.4 Tools Callibration of FMU 90 Prosonic meter 400,000 400,000
Replacement of Gravity dosers 2,400,000
1.5 Chebara Treated Water
Main &Water Distribution
Network
Replacement of Chebara DN 600 raw water valve
1,200,000
Replacement of Chebara backwash pump No.1 motor
250,000
Replacement of Chebara blower motors 500,000
Replacement of Chebara backwash pump No.2
1,000,000
Replacement of automanual step screen 800,000
3984 3984
Project 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029
1.6 Boundary Treatment Boundary 5.9kW submersible sludge pumps
4,000,000
Automation of Boundary pumping stations
2,500,000
Boundary 17kW submersible recirculation pumps
- 10,500,000
1.7 ICT Assets E-board(10No user license) 1,500,000 1,500,000 1,500,000 1,500,000
1.8 HQ FireProof Safe-HR 2,000,000
1.9 Kapsoya Treatment FireProof Safe-HR 1,800,000
Sub-Totals 8,900,000 8,000,000 35,350,000 33,800,000 7,800,000
2.0. Extension of sewer lines
2.1 Serwer Civil Contruction
Works
KIE Sewer Project - 10,457,670
Block 10 Sewer Project including branch 1 to branch 4
22,786,755
Last Mile connectivity 35,000,000
Salim Dola Sewer Project 3,167,640
Last Mile connectivity 35,000,000
Kipkorgot Sewer Extensions Project 19,270,152
Sub-Totals - - 33,244,425 38,167,640 54,270,152
3.0 Replacements of Sewer
Networks
Kona Mbaya Rehabilitation 754,860
Rehabilitations of Manholes - 6,853,200 - 6,853,200
Mwanzo Rehalitations - - 13,542,454
Kambi karatasi Sewer Project 5,833,184
GK Prisons 15,358,911
Sub-Totals 754,860 12,686,384 15,358,911 13,542,454 6,853,200
4.0 New Assets
Ellegrini Dam Fencing of the dam 1,000,000
Two Rivers Dam Fencing of the dam 1,000,000
Moben Dam Fencing of the dam 3,000,000
Kapsoya Treatment Purchase of 77 KVA Stanby Electric generator
3,500,000
Installation of Kapsoya CCTV 1,030,660
5.0 Chebara Treated Water
Main &Water Distribution
Network
Design and construction of aeration chamber at chebara drinking water treatment plant
11,221,028
6.0 ICT Assets Routers HQ and Areas 500,000
POE Network switches - - 500,000
Document Management System 7,000,000
ICT Assets tagging, tracking and managing
Software
240,000
Email & Website Hosting 1,000,000
E-board(10No user license) 1,500,000
7.0 ERP Movement to cloud Resource acquisition-Cloud( 1 TB hard drive space plus 100 GB RAM, 2 processor 16 cores)
5,000,000
Existing ERP and Billing Systems
Modules Maintenance + Enhancements for emerging new system changes/requirements
1,000,000 - 1,000,000
Acqusition and implementation of
Technical Processes Module(4 Water
Treatment Plants and 2 Sewarage
Plants)
8,000,000
Implementation of Automatic Dosing system-4No TWs
16,000,000
8.0 GIS customer identification survey 7,000,000
Purchase of 1No. RTK survey equipment
4,000,000
9.0 Quarry Treatment Automation of Quarryrecirculation pumping station
1,200,000
Automation of Quarry recirculation pumping station
1,800,000
10.0 Naiberi Treatment Plant Installation of Naiberi electrical winch 1,800,000
Installation on CCTV 697,180
Replacement of pumps 679,180
11.0 Lab Equipment Purchase of Atomic absorption spectrophotometer (AAS) for Elemental and heavy metal monitoring in water and waste water.
8,000,000
12.0 Motor Vehicles Purchase of 1No. double cab pick-up 7,500,000
14th August, 2026 THE KENYA GAZETTE
Project 2024/2025 2025/2026 2026/2027 2027/2028 2028/2029 for PDC
13.0 Storage facility Construction of KAPSOYA MAIN
STORE
7,000,000
Sub-Totals 20,461,028 7,000,000 37,727,840 25,179,180 11,800,000
17.0 NRW Reduction Sub-Totals - 15,037,680 44,537,680 38,287,680 40,037,680
18.0 Replacements of Water
Networks
Moi-Girls Dola Water Project - 18,001,640
Rehabilitation of water chambers 4,500,000
Eldoret West Replacement 10,695,321
Chebarus pipe replacement 7,155,540
Replacement of uPVC Pipes to HDPE 5,900,700
Rehabilitation of water chambers 4,500,000
Replacement of uPVC Pipes to HDPE 5,900,700
Munyaka-Bahati pipe replacement 22,985,626
Rehabilitation of water chambers 4,500,000
Replacement of uPVC Pipes to HDPE 5,900,700
4,500,000 15,195,321 23,902,340 40,541,866 5,900,700
19.0 Replacement of sewer network
Kamukunji Extension 2 21,493,290
Huruma Extensions 32,338,062
Langas Sewer Project 8,325,975
Harvad-High School Sewer 2,383,605
Slaughter Sewerline 5,504,935
- - - - 70,045,866
Total 34,615,888 57,919,385 190,121,196 189,518,820 196,707,598
Dated the 14th August, 2026.
RICHARD CHERUIYOT, Ag. Chief Executive Officer, MR/8284338 Water Services Regulatory Board.
Dated the 14th August, 2026.
RICHARD CHERUIYOT,
Ag. Chief Executive Officer, Water Services Regulatory Board.
Extracted Entities (3)
previous_gazette_ref
13176
12825
12825 of 2024
Details
- Act / Legislation
- THE WATER ACT
- Reference
- Cap. 372
- Section
- section 72 (1) (b)
- Signed By
- RICHARD CHERUIYOT
- Title
- Ag. Chief Executive Officer, Water Services Regulatory Board
- Date Signed
- 14th August 2026