GAZETTE NOTICE NO. 1351
PURSUANT to Clause 3 of Part III of the Schedule of Tariffs 2018, notice is given that all the prices for electrical energy specified in Part If of the said schedule will be liable to an inflation adjustment of plus 47 cents per kWh for all meter readings taken in February—June, 2022
Information used to calculate the inflation adjustment:
Last Half-year Period
INFA KenGen INFA IPP INFAKPLC Inflation Costs Under/Over Total
Recovery
Escalated Cost 518,720,100.73 621,645 ,651.34 1,589,118,346.19 (131,923 ,767.70) 2,597 560,330.57
Total projected units generated or purchased by the company in Jan—June, 2022 (Gp) = 6,288,466,574 kWh.
DANIEL K. BARGORIA, MR/3253364 Director-General.
Extracted Entities (1)
previous_gazette_ref
1351
Details
- Signed By
- DANIEL K. BARGORIA
- Title
- Director-General
- Page
- 20
- Extraction Method
- ocr-fallback
Source Gazette
Vol. CXXIV No. 26