GAZETTE NOTICE NO. 6480
GAZETTE NOTICE NO. 6480
THE WATER ACT
(No. 43 of 2016)
APPROVAL
in accordance with the requirements of section 139 of the Water
Act, 2016.
2228 2228
After considering the application, the written and oral submissions by all stakeholders during the consultation period, and based on latest available data, WASREB has determined a justified tariff to improve service delivery, operate sustainably and protect consumer interests by meeting the tariff conditions attached to the tariff.
WASREB notifies all existing and potential customers of
Karimenu II Dam Bulk Water Supply that the approved tariffs for the three financial years 2022/23, 2023/24 and 2024/25 shall be as follows:
1.0 Approved Bulk Tariff Structure
1.1 Bulk Water Tariff Structure for the Period 2022/2023 to
2024/2025
Approved Tariff (KSh./M3)
Sale per m3 36
2.0 Analysis of Cost Structure
Below is the summary of the projected annual cost structure that makes up the total costs to be incurred by Karimenu Bulk Supply during the tariff period:
Particulars
Average Annual
Revenue/Costs for the Period
Amount (KSh.)
Personnel Expenditure 37,190,799
Training 3,762,367
General Administration 12,584,327
Other Operational Expenditure* 78,868,987
Maintenance Expenditure 9,276,696
Total O&M Expenditure 141,683,175
Minor Investments
(i) Water supply to areas affected by construction of the dam
30,000,000
(ii) Fencing around the dam 12,000,000
(iii) Source protection works/ conservation activities
(Addressing pollution from
Kirache market)
18,000,000
(iv) Buffer zone acquisition 15,000,000
Loan Repayment (Interest Only) * 660,082,187
Total Expenditure 876,765,363
Average Revenue 901,698,663
Total Cost Coverage 103%
3.0 Conditions Attached to the Tariff Approval
The conditions attached to this approval which shall form part of the license conditions for Karimenu Bulk Water Supply are:
(a) Service Delivery Conditions Attached to the Tariff.
Target 2022/2023 2023/2024 2024/2025
Non-Revenue water 7% 7% 7%
Water Quality Standards 100% Compliance with all standards
Hours of Supply 24 24 24
Metering ratio 100% 100% 100%
Staff per 1million m3 billed (No.) 33 35 35
Collection Efficiency (%) 95% 95% 95%
Total Cost Coverage 103% 103% 103%
(i) Performance Evaluation
Performance targets to be met and ascertained by WASREB, at the end of the 1st year of the tariff period. Non achievement of the set targets without justifiable cause shall lead to reduction of the approved tariffs as a penalty.
(ii) Annual Budgets
The approved cost structure shall form the annual budget for the
Bulk Water Supply for each of the financial years of the tariff period.
(iii) Ring-Fencing of Capital Expenditure
The WSP to open a separate account for capital component of the tariff, to deposit the appropriate share of revenue into this account which is only to be used for capital expenditure and repayment of loans as provided for in the approved tariff.
(iv) Tariff Assessment
WASREB will carry out a tariff implementation review within the first 12 months of approval and implementation during which a joint assessment with the utility on the trend in Billing (KSh.) shall be carried out and status of implementation of the tariff evaluated.
(v) Loan Repayment
AWWDA shall immediately open a separate bank account where it shall deposit monthly equal instalments for the semi-annual loan repayments.
2023/2024 2024/2025 2025/2026
Loan Repayment
Amount (KSh.)
731,883,016 660,876,256 587,487,289
(b) Investments: The utility shall undertake the following investments within the tariff period and submit progress reports on a quarterly Basis.
Item
No. Item Description Estimated Cost
(KSh.)/Per Year
1. Water supply to areas affected by construction of the dam
30,000,000.00 a. Water Supply for Gathanji area 15,000,000.00 b. Water Supply for Kanyoni area 15,000,000.00
2. Fencing around the dam 12,000,000.00
Initial stage to include fencing of red zone areas - including areas near schools/ markets etc.
3. Source protection works/ conservation activities
18,000,000.00
Addressing pollution from Kirache market
4. Buffer zone acquisition 15,000,000.00
Initial acquisition of stage 1 buffer zone areas - areas affected by potential flood water within 1 year
Total (KSh.) 75,000,000.00
JULIUS ITUNGA, MR/5164675 Ag. Chief Executive Officer.
Dated the 19th May, 2023.
JULIUS ITUNGA,
Ag. Chief Executive Officer.
Extracted Entities (1)
previous_gazette_ref
6480
Details
- Act / Legislation
- THE WATER ACT
- Reference
- No. 43 of 2016
- Section
- section 72 (1)
- Signed By
- JULIUS ITUNGA
- Title
- Ag. Chief Executive Officer
- Date Signed
- 19th May 2023