GAZETTE NOTICE NO. 6178
PURSUANT to clause 5 of Part III of the Schedule of Tariffs 2018, notice is given that all prices for electrical energy specified in Part II -(A) of the said schedule will be liable to a Water Resource Management Authority (WRMA) levy of plus 1.74 Cents per kWh for all meter readings taken in
May 2022
Information used to calculate the WRMA levy:
Approved WRMA levy for energy purchased from hydropower plants of capacity equal to or above 1MW =5.00 Kenya cents per KWh
Hydropower Plant
Units Purchased in April 2022 (kWh)
Gitaru
52,052,990
Kamburu
27,550,070
Kiambere
43,928,210
Kindaruma
12,613,430
Masinga
9,016,240
Tana
5,692,370
Wanjii
3,684,745
Sagana
548,397
Turkwel
49,473,970
Gogo
420,003
Sondu Miriu
15,544,000
Sangoro
4,816,290
Regen-Terem
761,910
Chania
43,580
Gura
1,445,882
Metumi
735,539
Total units purchased from hydropower plants with capacity equal to or above 1MW = 228,327,625 kWh
Total units generated and purchased (G) excluding exports in April 2022 = 1,032,424,563 kWh
DANIEL K. BARGORIA, Director General.
MR/3253364
27th May, 2022
Extracted Entities (1)
previous_gazette_ref
6178
Details
- Signed By
- DANIEL K. BARGORIA
- Title
- Director General
- Date Signed
- 27th May 2022
- Page
- 50
- Extraction Method
- regex
Source Gazette
Vol. CXXIV No. 96
Published 6th February 2022