Back
REGULATION 100% confidence via regex

GAZETTE NOTICE NO. 2525

GAZETTE NOTICE NO. 2525

THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT

(No. 8 of 1999)

REGULATION


Pursuant to Regulation 21 of the Environmental Management and Co-ordination (Impact Assessment and Audit) Regulations, 2003, the National Environment Management Authority (NEMA) has received an Environmental Impact Assessment Study Report for the above proposed project. The proponent, Deer Premium Investment Limited, is proposing to construct three blocks of nine {9, (ground + 8)} floors comprising of one hundred and eighty eight (188) housing units, 174 basement parking bays and 181 ground floor parking bays; the ground floor will also have a minm market, children play area, garden area, water feature (fountain) security house and drive ways; the first floor of all the blocks will each have 6No. three (3) bedroom units, block A and B will have 5No. and 6No. detached servants quarters respectively, Block C will have management office, swimming pool deck and gymnasium on the second floor. 3rd to 8th floors of all the three Blocks will each have 8No. three (3) bedroom units and 6No. DSQ for Block A and 8No. DSQ each for block B and C, and other auxiliary facilities on plot L.R. No. 27702/6, 12883/19 and 12883/20 in Syokimau area, Movoko Sub- County, Machakos County. The following are the anticipated impacts and proposed mitigation measures: Impacts Proposed Mitigation Measures Soil erosion • Implement soil erosion control measures and compact soil in open areas. Effluent discharge • Provide a sewer connection line to MAVWASCO sewer line. • Monitor effluent quality regularly to ensure that the stipulated discharge rules and • standards are not violated. • Ensure that no waste water is discharged directly into the immediate environment. • Ensure that convenience facilities are adequate for all the employees on site and are cleaned on a daily basis. Increased energy • Advocating for the use of other renewable use sources of energy such as wind and solar energy, install solar panels. • Use of clean fuels e.g. unleaded and de- sulphurized fuels in vehicles. • Paving should only be carried out where necessary to reduce the reflection of the solar radiations. • Using sustainable drainage systems that mimic the natural percolation of water into the soil, and green roofs where possible. Noise pollution • Ensure that construction machinery are kept in good condition through regular servicing and maintenance to reduce the amount of noise generated during use. • All construction activities must be limited to between 8 a.m. and 5 p.m. during weekdays. • No heavy construction activities/ noise generating 'activities shall be undertaken on Sundays and public holidays. • No construction activities shall be carried out on site at night. • No blasting of stones if any shall be carried out within the project without prior notice being issued. • Comply with EMCA (Noise and Excessive Vibration Pollution Control) Regulations, 2009. • Ensure that all workers are provided with and wear PPE at all times. • Ensure use of suppressors or noise shields on noisy equipment. Solid waste • Waste minimization by avoiding generation unsustainable construction practices. • Provision of waste collection bins and cubicles for collection and temporal holding of the generated waste within the site before disposal. • Provide solid waste handling containers within the project site to help in proper collection and management. 15th March, 2019 THE KENYA GAZETTE 1067 Impacts Increased water demand Air pollution Proposed Mitigation Measures • Contract a registered and licensed waste collection company to assist in the disposal of the generated and collected solid waste to the County's designated final disposal site. • Ensure separation at source of the solid waste generated on site is done to enhance reusing of any material recovery. • Sensitize construction workers on the importance of proper water managerrient. • Replace or repair leaking pipes supplying water to the construction sites to minimized wastage from leakages or pipe burst. • Ensure provision of adequate water storage facilities on the construction site to meet project needs during periods of high demand externally and refill of storage tanks during periods of low demand. • Reuse of waste water from the construction activities for curing of concrete surfaces and cleaning of equipment so as to reduce on the fresh water use. • Direct construction water run-off to areas where it can soak into the ground or be collected and reused. • Lock water tank valves to prevent unauthorized use and discourage wasteful use of water by construction workers. • Repair water equipment as needed, to prevent unintended discharges. Equipment such as water trucks and water reservoirs need to be inspected on a regular basis and incase of damage or fault, repairs should be undertaken immediately. • Install smart water meters and showers with Infra-red Radiation sensors to control water use during occupation.. • Avoid excavation works in extremely dry weather when soil is pulverized. • Ensure all trucks delivering construction materials such as sand or those transporting wastes dare properly covered to prevent the spread of dust. • Ensure proper planning of transportation of materials to ensure that vehicle fills are increased in order to reduce the number of trips done per vehicle. Impacts .Proposed Mitigation Measures Fire • Smoking on site or burning of waste should be prohibited so as to reduce the source of ignition at the site. • Electrical works such as electrical wiring should be done by qualified technicians or • Place portable fire extinguishers at suitable locations. • Train and induct workers on the 'use of fire extinguishers and other fire-fighting equipment. • Designate a fire assembly point. • Ensure fire safety warnings are prominently displayed at appropriate locations where fires are likely to occur. The full report of the proposed project is available for inspection during working hours at: (a) Director-General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839-00200, Nairobi. (b) Principal Secretary, Ministry of Environment and Forestry, NHIF Building, Community, P.O. Box 30126-00100, Nairobi. (c) County Director of Environment, Machakos County. The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the Director-General, NEMA, to assist the Authority in the decision making process of the plan. GEOFFREY WAHUNGU, Director-General, MR/6019912 National Environment Management Authority.

Dated the 15th March, 2019.

GEOFFREY WAHUNGU,

Director-General, National Environment Management Authority.

Extracted Entities (1)

previous_gazette_ref

2525

Details

Act / Legislation
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
Reference
No. 8 of 1999
Signed By
GEOFFREY WAHUNGU
Title
Director-General, National Environment Management Authority
Date Signed
15th March 2019
Page
44
Extraction Method
regex