GAZETTE NOTICE NO. 1273
GAZETTE NOTICE NO. 1273
THE ENVIRONMENTAL MANAGEMENT AND CO - ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of Environmental (Impact
Assessment and Audit) regulations, the National Environmental
Management Authority (NEMA) has received an Environmental
Impact Assessment Study Report for the implementation of the
Proposed Ecolodge at Hagenia, Aberdare National Park.
The project entails construction of a 30 bed eco-lodge that shall consist of one-level structures on elevated wooden decks and with semi-permanent solid walls of natural materials that blend well with the environment with minimum concrete. In addition it will comprise of 15 luxury cabins, a club house, swimming pool and private lone huts for dining and bird watching.
The proposed project will be located at Hagenia site within
Aberdare National Park on a 35 acre piece of land. The site is six kilometres south-west of Chania River and the Chania Picnic site.
The following are the anticipated impacts and proposed mitigation measures:
Environmental issue
Mitigation Measures
Hydrology and
Drainage
Existing and new tracks should have provisions for side drains, mitre drains and culverts all located at appropriate points, that is, employing the principle of discharging water off the road little and often, particularly on sloped terrain.
The drains must lead to the safest point of
3rd February, 2012 THE KENYA GAZETTE discharge (usually a water course).
These structures must be regularly maintained.
Soil Erosion Only minimal bush clearing should be done
With regard to creating and or gravelling of tracks, if recommendations for frequent drainage off the road are taken into consideration, then erosion will be minimized. The installation of check-dams
(using sticks and stones, or naturally occurring biological material) and scour checks along the drains will also prevent erosion. Again these structures must be regularly maintained.
Excavations of the site will be confined only within the sections upon which constructions is taking place.
Excavated earth will be held away from locations of the site not susceptible to surface runoff of storm water.
The earth removed from external disposal will require to be deposited on sites without the risk of being washed down during rains and where it will not compromise other land use activities in those areas.
Extra precautions on control of soil erosion will be required on construction during periods of heavy rainfall.
Re-vegetate exposed areas on the site so as to mitigate further erosion of soil.
Landscaping with indigenous species will help to mitigate soil erosion during the operation phase of the project.
Water
Resources
Flows rates in the River or springs that are intended to be used as water sources should be established
The Proponent should liaise with WRMA to obtain the necessary permit to draw water
River water used for the eco-lodge‘s supply will have to be tested and treated accordingly. Parameters for testing should include suspended solids, nitrates, phosphates, pH, conductivity, organic matter and fluoride.
Care should be taken to ensure that water tapped comes right from the source. Dosing with chlorine should be sufficient for the purposes of the eco-lodge, as this water is not intended for potable use. This can be done through automated procedures or manually, but whichever method is chosen, it is important that the residual concentration of 0.2 to 0.5 mg/l (depending on bacterial contamination levels) after 30 minutes of contact time is maintained in order to ensure bacterial disinfection.
Good environmental practice would entail properly recording and filing water treatment procedures, so that in the absence of the person normally responsible for treatment of water, any other assigned person is able to competently carry out this function.
In the same vein, guests as well as staff should be sensitized with regard to minimizing water usage.
In order to reduce water consumption, guests should be encouraged not to have their clothes washed while they are at the
Ecolodge. In addition, camps should arrange to take their linen, uniforms etc to
Nyeri or Nairobi for washing.
Noise and
Vibrations
Ensure that construction equipments are maintained at the best operating conditions to avoid unnecessary noise.
All equipment and machinery must be regularly maintained.
Guests must be advised to keep noise levels down, especially when watching game.
Playing radios and ghetto-blasters should not be permitted within the Ecolodge.
Hooting must also be prohibited.
Driver guides should adhere to Kenya
Association of Tour Operators (KATO) codes of ethics, especially during game drives.
Ensure workers are provided with the necessary personal protective equipment including earplugs or earmuffs when operating or working with noisy equipment.
Power generators should be installed in acoustically designed structures to prevent noise pollution.
Air Quality Drivers are advised to avoid idling and unnecessary idling of their vehicles while within the Park
Regular servicing of vehicles to avoid emitting of fumes beyond the required levels
Solid Waste Proper disposal of construction wastes and debris outside the National Park at approved dump site.
Segregate waste
Adopt reduce, reuse, recycle philosophy
Waste to be taken to Nairobi until suitable local options is available.
Train local communities to recycle/ reuse waste
Construction/
Burrow
Materials
Bonafide/ environmentally friendly materials sources
Restricted use of certain specified materials
Burrow pits to be located outside the
National Park, ensure controlled excavation, and rehabilitation after use.
Aberdares
National Park
Monitor locations of wildlife within the
National Park.
Implementation of the Management Plan for the Forest Ecosystem and the National
Park.
Vegetation Prohibit off-road driving
Encourage neighbouring communities to grow vegetables to supply the camps
Prohibit planting of non-endemic species in the National Park.
Encourage communities to grow wood for campfire and energy sources
General risks and hazards
Provision and maintenance of firefighting equipment
Emergency response plans and training
Visual aspects Locate facilities discretely
Design structures to complement environment
Camouflage structures
The full report of the proposed project is available for inspection during working hours at:
(a) Director General, NEMA, Popo Road, off Mombasa Road, P.O.
Box 67839-00200, Nairobi.
(b) Permanent Secretary, Ministry of Environment and Mineral
Resources, NHIF Building, Community, P.O. Box 30521, Nairobi.
(c) Provincial Director of Environment, Central Province.
(d) District Environment Officer, Nyandarua District
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director General, NEMA, to assist the Authority in the decision making process of the plan. (EIA/5/2/786)
SALOME MACHUA , For: Director General, MR/8844590 National Environment Management Authority.
Dated the 3rd February, 2012.
SALOME MACHUA,
For: Director General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
1273
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO - ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- SALOME MACHUA
- Title
- For: Director General, National Environment Management Authority
- Ministry
- Ministry of Environment And Mineral
- Date Signed
- 3rd February 2012
- Page
- 68
- Extraction Method
- regex
Source Gazette
Vol. 8 3rd February 2012.pdf
Published 5th June 1980