GAZETTE NOTICE NO. 15753
GAZETTE NOTICE NO. 15753
THE KENYA GAZETTE 4709 THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of Environmental (Impact
Assessment and Audit) Regulations, the National Environment
Management Authority, (NEMA) has received an environmental impact assessment study report for the implementation of the proposed
Baraka estate phase 3.
The proposed development will include construction of a residential estate of 101 units of three types:
(a) Type C—Maisonettes
(b) Type D—Maisonettes
(c) Type F—Maisonettes
The project site is located on Plot L.R. No. 18111 in Embakasi, off
North Old Airport near Administration Police Training College
(APTC).
The following are the anticipated impacts and proposed mitigation measures:
Possible Impact Mitigation measures
Vegetation Disturbance Ensure proper demarcation and delineation of the project area to be affected by the construction work.
Specify location for vehicles and equipment and areas of the sit which shall be kept free of traffic equipment and storage.
Designate access routes and parking within the site.
Introduction of vegetation(trees, shrubs and grass) on open spaces and around the project site and their maintenance.
Design and implement an appropriate landscaping progamme to help in re- vegetation of part of project area after construction.
Increased solid waste generation
Use of an integrated solid waste management system i.e. through a hierarchy of options: 1. Reduction at source, 2. Recycling, 3. Reusing, 4.Incineration, 5. Sanitary Land filling.
Through accurate estimation of the dimensions and quantities required.
Use of durable, long lasting materials that shall not need to be replaced as often as, thereby reducing the amount of waste generated over time.
Provide facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements.
Use building materials that have minimal or no packaging to avoid generation of excessive packaging waste.
Reuse packaging materials such as cartons, cement bags, empty metal and plastic containers to reduce waste at site.
Dispose waste more responsibly by contacting a waste registered handler who will dispose the wastes at designated sites only.
Waste collection bins to be provided at designated points only.
Dust Emission Ensure strict enforcement of on-site speed limit regulations.
Sprinkle water during excavation works by heavy machines.
Sprinkle water on graded access routes when necessary to reduce dust generation by construction vehicles.
Dust masks to be provided to employees and worn.
Use environmentally friendly fuels
Minimize the period for machinery idling.
Pursue good practices in energy use during operations and sensitize staff.
Provide appropriate personnel protective equipment to site workers.
Health and Safety Comply to the OSHA.
Provide personnel and passers-by signage and warnings traffic control signs and warning.
Develop a traffic management plan to ensure that site vehicles do not interfere with the regular traffic on the Project area.
Provide for appropriate signage and warnings at work sites.
Provide appropriate personnel Protective
Equipment (PPE) to site workers.
Provide for First Aid facilities as per the
OSHA, 2007.
Provide for an appropriate traffic management plan to avoid congestion on road leading to her project area.
Provide and clearly display emergency contacts.
Develop and implement detailed and site specific Emergency Response Plans.
Fire hazards Ensure fire extinguishers are stationed in visible places.
Security personnel and occupants to be trained in fire fighting skills.
Drilling exercise to be conducted regularly.
Train substation operators on firefights.
Install smoke fire detectors and fire alarms.
Noise and Vibrations Sensitize construction vehicle drivers and machinery operators to switch off engines or machinery not being used.
Sensitize the construction vehicle drivers to avoid avoiding unnecessary hooting.
Ensure that construction machinery are kept in good condition to reduce noise generation.
Sound barriers to be elected round the construction site.
The noisy construction.
Works should be entirely planned to be during day time.
Increased storm water, runoff and soil erosion
Surface runoff and roof water shall be harvested and stored in reservoirs so that it can be used for other purposes within the project site.
A storm water management plan that minimizes impervious area infiltration by use of recharge areas and use of retention with graduated outlet structures
THE KENYA GAZETTE 9th December, 2011
4710 4710 shall be designed
Apply soil erosion control measures such as levelling of the project site to reduce run-off velocity and increase infiltration of storm water into the soil.
Ensure that construction vehicles are restricted to use the graded roads.
Ensure that compacted areas are ripped to reduce run-off.
Oil Spills Install oil trapping equipments in areas where there is a likelihood of oil spillage such as during the maintenance of construction of maintenance equipment.
Soil in such an area shall be well protected from contamination.
The full report of the proposed project is available for inspection during working hours at:
(a) Director-General, the National Environment Management
Authority (NEMA), Popo Road, off Mombasa Road, P.O. Box
67839–00200, Nairobi.
(b) Permanent Secretary, Ministry of Environment and Mineral
Resources, N.H.I.F. Building, Community, P.O. Box 30521, Nairobi.
(c) Provincial Director of Environment, Nairobi Province.
(d) District Environment Officer, Embakasi and Makadara
Districts.
The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the approval process of the project.
B. M. LANGWEN, for Director-General, MR7681871 National Environment Management Authority.
Dated the 9th December, 2011.
B. M. LANGWEN,
for Director-General, MR7681871 National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
15753
Details
- Act / Legislation
- THE KENYA GAZETTE 4709 THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- B. M. LANGWEN
- Title
- for Director-General, MR7681871 National Environment Management Authority
- Ministry
- Ministry of Environment And Mineral
- Date Signed
- 9th December 2011
- Page
- 94
- Extraction Method
- regex
Source Gazette
Vol. CXIII No. 119