GAZETTE NOTICE NO. 8813
PURSUANT to clause 2 of part III of the Schedule of Tariffs 2008, notice is given that all prices for electrical energy specified in part II of the said schedule will be liable to an inflation adjustment of plus 17cents per kWh. for all meter readings taken in July-December, 2011.
Information used to calculate the adjustment:
INFAKenGen INFA IPP INFAKPLC Last Half-year Period inflation costs under/(over) Recovery
TOTAL
Escalated cost 169,810,428.47 78,659,223.95 282,102,308.23 3,588,245.63 534,160,206.28
Total projected units generated or purchased by the company (Gp) = 3,808,032,133
L. K. NJAGI, Company Secretary.
Extracted Entities (1)
previous_gazette_ref
8813
Details
- Signed By
- L. K. NJAGI
- Title
- Company Secretary
- Page
- 71
- Extraction Method
- regex
Source Gazette
Vol. CXIII No. 67
Published 22nd July 2011