Back
REGULATION 100% confidence via regex

GAZETTE NOTICE NO. 1246

GAZETTE NOTICE NO. 1246

THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT

(No. 8 of 1999)

REGULATION


PURSUANT to regulation 21 of Environmental (Impact Assessment and Audit) Regulations, the National Environment Management Authority, (NEMA) has received an environmental impact assessment study report for the implementation of the proposed filling station. The proposed development involves construction of a filling station comprising of: 5 dispensing pumps (2 for petrol, 2 for diesel and 1 for kerosene). 3 underground storage tanks; a canopy; tire centre. Office block (lubricants shop, reception, office, and toilets). The proposed project site will be on plots no. Ruiru East Block 1/T.866 and T.867 measuring 0.5 Ha and .0.0640 ha respectively and located along Thika- Nairobi Highway about 2 kilometers from Ruiru town at a place called Kihunguro. The following are the anticipated impacts and proposed mitigation measures Possible Environmental Impacts Suggested Mitigation Measures Blockage of storm drainage system Ensure that storm drainage system remains clear during construction. Soil from the site which is not in use should be properly disposed. Air pollution Sprinkle water on dusty surfaces. Place the concrete mixer in well ventilated area. Ensure the workers wear proper PPEs (including dust masks). Noise and vibrations Construction activities must be carried between 0800hrs and 1700hrs. Use light vibrators. Regular servicing of machines and equipment. Lubrication of machines. Compliance with Noise and Vibration regulations. 11th February, 2011 THE KENYA GAZETTE 429 Possible Environmental Impacts Suggested Mitigation Measures Occupation health and safety Provision of PPE/C to worker during construction time. The PPE should include Overalls/Aprons, helmet, dust masks, wielding shield/goggles, ear muffs or plugs (where necessary), and appropriate footwear. Provide first Aid facilities emergency plan at the site. Fencing off the developing project to avoid risks to the general public. Supervision of the project should be done throughout the project implementation period. Waste Management Waste should be disposed at the designated municipal site. Contract a licenced waste collector. Provision of rubbish bins. Segregation of wastes at the source. Solid waste should be managed according to the waste management regulations. Fire risks Install fire extinguishers at the filling station. Clearly mark fire exit points and the fire assembly area. Provide sand buckets at strategic locations. Workers should be trained on fire fighting skills by a qualified trainer. Fire drills should be conducted at least once a year. A fire fighting team should be established. Warning and informational signs be displayed appropriately. Conduct fire audit once a year. Formulate and bring to the notice of all workers and clients fire safety policy and rules. Regular testing and servicing of fire- fighting equipment and appliances. Full compliance with the Fire Risk reduction Rules, 2007. Oil spills Pumps should be inspected regularly. Pump valves should be well fitted. Dispenser pipes and underground tanks should be of approved quality standard. Regular monitoring to detect leakages from tanks and pipes. Install an oil interceptor in the drainage system. Recovery of waste oil for proper disposal by authorized agent. Use oil absorbent material to clean oil spills especially at the service bay. Regular checking/monitoring of the drainage lines, interceptor and the water sump to ensure that are working effectively without any overflow or failures. Possible Environmental Impacts Suggested Mitigation Measures Ensure that the underground tanks are compliant with Kenya standards (KS 200:2002). Conduct pressure tests before commissioning of the station to ensure that the product lines (pipe works) comply with KS 1969:2006, KS 1967: 2006 and 1968: 2006. The full report of the proposed project is available for inspection during working hours at: (a) Director-General, the National Environment Management Authority (NEMA), Kapiti Road, off Mombasa Road, P.O. Box 67839–00200, Nairobi. (b) Permanent Secretary, Ministry of Environment and Mineral Resources, N.H.I.F. Community, P.O. Box 30521, Nairobi. (c) Provincial Director of Environment, Thika East/West District. The National Environment Management Authority invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the Director-General, NEMA, to assist the Authority in the approval process of the project. A. M. KARIUKI, for Director-General, MR1216391 National Environment Management Authority.

Dated the 11th February, 2011.

A. M. KARIUKI,

for Director-General, MR1216391 National Environment Management Authority.

Extracted Entities (1)

previous_gazette_ref

1246

Details

Act / Legislation
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
Reference
No. 8 of 1999
Signed By
A. M. KARIUKI
Title
for Director-General, MR1216391 National Environment Management Authority
Date Signed
11th February 2011
Page
42
Extraction Method
regex