Back
ACT
100% confidence
via regex
GAZETTE NOTICE NO. 8678
GAZETTE NOTICE NO. 8678
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ACT
PURSUANT to section 59 of the Environmental Management and
Co-ordination Act, 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, Ken Petrogas Limited, proposes to construct a
Liquified Petroleum Gas (LPG) and Liquified Natural Gas (LNG)
Terminal and Jetty comprising of 2No. 5000 metric tonnes LPG
storage tanks, 6No. trucks loading bay, 4No. 35,000 cubic meters LNG
storage tanks, 2No. 10 million water storage and fire pumps, floating
offloading jetty, trucks parking, marshalling yard, terminal control
room, LPG pumps and compressors, weighbridge, administration
office block, perimeter masonry wall, security station, associated
facilities and amenities on plot No. Kwale/Shimoni ADJ/441, Kwale
County.
THE KENYA GAZETTE 27th June, 2025
The following are the anticipated impacts and proposed mitigation
measures:
Impacts Proposed Mitigation Measures
Noise and vibration • Clear lines of communication will be
developed between the project team,
contractors and any affected premises.
• Construction work will be carried out
during daytime only, where possible. If
night working is required, the contractor
should inform and agree with local area
residents and concerned agencies.
• All vehicles and mechanical plant used
for construction should be fitted with
effective exhaust silencers, and regularly
maintained.
• Compressors and pumps should be
positioned so as to cause minimum noise
disturbance. If necessary, temporary
acoustic barriers or enclosures should be
provided.
Increased solid and
effluent waste
generation
• Segregate waste at point of generation.
• Any hazardous waste material will be
sited on an impervious base within an
oil-tight bund with no drainage outlet.
• Liquid waste, including solvents and oil,
will be securely stored in bunded
compounds prior to collection by a
registered waste handler.
• In the event of a spill, immediate clean-
up will be undertaken. It is
recommended that appropriate spill kits
or absorbent materials are held on site.
• Waste water (sewage) from the
construction camp will be channeled into
the existing sewer trunk.
Occupational safety and
health
• The site must be fully fenced (hoarding)
to prevent unauthorized access onto the
site.
• Potentially hazardous areas must be
demarcated and clearly marked.
• Design suitable documented emergency
preparedness and evacuation procedures
to be used during any emergency.
• Provide measures to deal with
emergencies and accidents including
adequate first aid arrangements and
provision of emergency telephone
numbers.
Increased traffic • A Driver Code of Conduct will be
implemented stipulating and governing
safe driving behavior, which will include
no use of cell phones whilst driving.
• All vehicles should not exceed the
mandated speed limits of 30km/h.
• A Traffic Management Plan will be
developed and implemented, with at
least the following provisions included: -
• All drivers will be sensitized to
potential accident risks;
• All vehicles will be regularly
checked and maintained in good
condition.
Fire, explosion (LPG
leaks)
• Install continuous gas detection systems
that monitor for LPG leaks in critical
areas such as tanks, pipelines, and
valves.
Impacts Proposed Mitigation Measures
• Use flame arrestors and explosion-proof
equipment in areas where leaks might
occur.
• Install deluge or water spray systems in
areas of high risk, such as tank farms and
loading/unloading areas.
• Apply foam-based fire suppression
systems in areas with high flammability
risks (such as storage tanks) to suppress
fires quickly and prevent LPG vapor
ignition.
• Place portable fire extinguishers near
critical areas (both class B – for
flammable liquids, and class C – for
electrical fires).
• A permanent warning sign must be
installed at the entrance to the site.
• The Emergency Evacuation Procedure
aimed at workers and visitors must be
updated at least annually in collaboration
with the Mombasa County, VTTI, KPC,
KMA and KPA emergency services.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Foresty, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, Upper Hill, P.O. Box 30126–00200,
Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Kwale County.
A copy of the EIA report can be downloaded at www.nema.go.ke
The National Environmental Management Authority, invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA to assist the Authority in the decision
making process for this project.
Comments can also be e-mailed to dgnema@nema.go.ke
MAMO B. MAMO,
MR/7783059 Director-General,
Dated the 27th June, 2025.
MAMO B. MAMO,
Director-General,.
Extracted Entities (1)
previous_gazette_ref
8678
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General,
- Date Signed
- 27th June 2025
- Page
- 35
- Extraction Method
- regex
Source Gazette
Vol. CXXVII No. 139
Published 30th January 2025