GAZETTE NOTICE NO. 13880
GAZETTE NOTICE NO. 13880
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
TRANSFER
PURSUANT to section 59 of the Environmental Management and
Coordination Act, 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent Wang-Tech Petroleum Limited intends to set up
used oil transfer station and asbestos disposal site and incinerator
comprising of an office block, used oil decanting chamber, incinerators,
an open yard complete with storm water drains, waste management
facilities, perimeter fence, E-waste holding area, temporary asbestos
holding shade, dismantling space on plot L.R.No. 3290/Kalumani,
Mnyenzeni, Kilifi County.
The following are the anticipated impacts and proposed mitigation
measures:
Impacts Mitigation Measures
Noise generation • Reduction of idling time of vehicles which are
not in use
• Increase attention to maintenance of tools and
equipment
• Regular inspection and servicing of the various
machines and power tools
Impacts Mitigation Measures
• Warn drivers to avoid unnecessary hooting of
vehicles
• Enclosure of noisy equipment with temporary
barriers
• Conduct periodic noise measurements and
monitoring
• Carry out project cycle activities between 8.00
a.m. and 5.00 p.m.
• Where noise exceeds 85dB (A) workers should
be provided with appropriate hearing
protection and their use enforced
Gaseous
emissions
• Ensure all fuel powered construction
equipment are serviced and maintained
regularly
• Unnecessary reversing and idling should be
discouraged
• The contractor shall carry out routine vehicle
maintenance and other machinery as per the
manufacture’s specifications to ensure
minimum emissions of gases such as NO2 and
SO2.
• Municipal waste should not be routinely
composted before disposal, and certainly not in
open air windrows.
• Provide public education and awareness on
environmental safeguards and protection
measures of the project.
Oil spillage
and/or leakages
• Installation and maintenance of oil interceptor
• Maintenance and regular inspection of above
ground used oil storage tanks
• Document spill prevention procedure &
response plan
• Major maintenance operations to be carried
out offsite
• Maintain appropriate spill response kits at the
site
• Use of drip trays for minor servicing of
equipment
• Used oil containers should be stored in closed
containers placed on water proofed surface and
protected from direct sunlight and rainfall
• Minimize the quantity of hazardous materials
stored at the site
• Use appropriate siphoning equipment to
transfer recycled oil from storage tanks onto
tankers to avoid oil spills
• Inspect transportation tankers and
reception/storage tanks to check checked for
any leakages
• In the event of an accidental spillage:
Ø Take immediate steps to avoid the
spillage spreading
Ø Keep other people and vehicles away
from the site
Ø Wear protective clothing appropriate to
the use of the
Ø hazardous material
Ø Soak up the hazardous material with
absorbent material
Ø such as dry san
26th September, 2025 THE KENYA GAZETTE
Impacts Mitigation Measures
Ø Decontaminate any remaining traces of
spillage on surfaces
Waste generation
and disposal
• Provide suitable solid waste containers
• Segregate waste as necessary
• Contract a waste transporter with a valid
license from NEMA to collect waste from the
site for disposal
• Construct suitable pit latrines for use by
construction workers on site
• Used oil should be accumulated in suitable
labelled containers for recycling during project
operation phase
• Safely accumulate oily rags for collection and
incineration by NEMA licensed incinerator
operators
• Implement an oil skimming programme for
oil/water interceptors to ensure normal
functioning
Falls and injuries
from elevated
and overhead
work
• Provide safety nets/traps prior to commencing
work at height
• Use of appropriate notices and signage to warn
workers against falling objects
• Restrict access to the site by unauthorized
personnel
• Ensure statutory inspection of all lifting
equipment (Chain blocks and cranes)
• Ensure cranes are operated only by trained and
experienced personnel
• Lifting equipment should not be overloaded
• Provide safety harnesses and scaffolding while
working at high levels
• Provide appropriate personal protective
equipment (helmets, safety boots, coveralls)
• Provide appropriate number of first aid kits
which should be restocked on regular basis
• Adequate number of workers to be trained on
first aid administration
• Names of trained first aiders to be
conspicuously displayed at the site
• Maintain a record of incidents & accidents on
site
• Document the procedure for working at
heights.
Fire • Provide appropriate firefighting equipment
• Train workers on fire fighting
• Ensure inspection of the fire equipment
• Post No smoking signs at the storage area for
the fuel and/or oil
• Designate a fire assembly point
• Provide and maintain a well-stocked first aid
kit
Occupational
health and
safety risks
• Construction of a site office for coordinating
construction activities
• Appoint a responsible person to be oversee all
health and safety issues
• Document appropriate emergency response
procedures
Impacts Mitigation Measures
• Employ security guards from reputable firms
• Document and display at the site emergency
contacts
• Obtain indemnity cover for all the workers on
site
• Provision of wholesome drinking water to
workers
• Use permits to work for critical tasks such as
electrical installations and hot works (welding)
• Maintain a register of workers on site
• Designate an emergency assembling point
• Hold pre-job and monthly safety meetings
with the hired workers to discuss safety issues
pertinent to the job
Increase of
transmission
communicable
diseases
• Refuse will be disposed onto the same area as
other inorganic wastes to deteriorate the
capacity of breeding sources.
• Insecticide should be used to control threshold
density of the houseflies that may include Fly
baits.
• A surface-active agent or polyoxyethylene
lauryl ether (PEL), should be used effectively
for the suppression of the fly density.
• Sticky traps can also reduce houseflies in
households
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Foresty, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, Upper Hill, P.O. Box 30126–00200,
Nairobi.
(b) Director General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Malindi County.
A copy of the EIA report can be downloaded at www.nema.go.ke
The National Environmental Management Authority, invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director General, NEMA to assist the Authority in the decision
making process for this project.
Comments can also be e-mailed to dgnema@nema.go.ke
MAMO B. MAMO,
Director-General,
MR/7784314 National Environment Management Authority.
Dated the 26th September, 2025.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
13880
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 26th September 2025
- Page
- 62
- Extraction Method
- regex
Source Gazette
Vol. CXXVII No. 200
Published 28th February 2025