GAZETTE NOTICE NO. 12192
GAZETTE NOTICE NO. 12192
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ACT
PURSUANT to section 59 of the Environmental Management and
Coordination Act 1999, the National Environment Management
Authority (NEMA) has received an Environmental Impact Assessment
Study Report for the above proposed project.
The proponent, Everwood Properties Limited, proposes to develop a 26-Storey (2No. basements, ground floor, 2No.mezzanine floors plus
26 floors) residential building comprising a total of 312 units (264No.
one-bedroom units and 48 No. two-bedroom units) 2No. Shops, gym, restaurant, parking spaces and other associated facilities and amenities on plot L.R. No. Nairobi/Block 34/180 (Original L.R. No. 209/65/29) along Mogotio Road, in Westlands, Nairobi City County.
The following are the anticipated impacts and proposed mitigation measures:
Impacts Proposed Mitigation Measures
Soil erosion • Control earthworks.
• Install drainage structures to control flow of storm water.
• Ensure and management of excavation activities.
Loss of vegetation • Only area earmarked for development should be cleared.
• Plant trees, shrubs and flowers on remaining open spaces.
Changes in hydrology/ impended drainage/deep excavations
• Proper Installation of drainage structures.
• Install cascades to break the impact of water flowing in the drains.
• Ensure efficiency of drainage structures through proper design and maintenance.
• Provide gratings to the drainage channels.
• A geotechnical survey shall be conducted and the recommendations thereof followed. There shall be no blasting during excavation.
• A methodology for excavation shall be generated as required by NCA.
Air pollution • Stockpiles of earth should be sprayed with water or covered during dry seasons.
• Provide dust masks for personnel in dusty areas.
• Sensitize construction workers on pollution control measures.
• Cover all trucks hauling soil, sand and other loose materials.
Noise pollution • Install suitable barriers to shield compressors and other small stationary equipment where necessary.
• Display signs to indicate construction activities.
• Maintain all equipment.
• The working hours should be in line with NEMA licensing conditions.
• Adhere to provisions of Noise
Prevention and Control Rules 2005, Legal Notice No. 24 regarding noise limits at the workplace as well as
NEMA Noise Excessive Vibration
Pollution Control Regulations, 2000.
Public health, • Train staff/workers on occupational
29th August, 2025 THE KENYA GAZETTE
Impacts Proposed Mitigation Measures occupational health and safety health and safety.
• Provide full protective gear and workmen’s compensation cover in addition to the right tools and operational instructions and manuals during construction.
• Design of sewerage system should be as provided in the plans and should be constructed to approved size and design, standard and of approved materials.
• Ensure use of standard construction materials and to the specifications.
Avoid undesirable, substandard, hazardous or unauthorized materials during construction and maintenance.
• Sensitized staff on social/health issues such as drugs.
Road traffic disruption • No overloading of trucks and good driving practices to be practiced.
• Suitable junction/access point to be provided.
• Use of appropriate & legible signage.
• Employment of formal flagmen/ women to ensure the public safety.
• Follow the recommendations of the traffic management plan.
Insecurity and social impacts
• Provision of security guards, CCTV cameras, security lights and other security apparatus during the entire project cycle.
• Construction work timings shall only in line with the NEMA licensing conditions.
Increased water usage • An alternative water source shall be provided. The proponent shall drill a borehole at the proposed site.
• Management of water usage. Avoid unnecessary wastage.
• Recycling of water at the construction phase where possible.
• Make use of roof catchments to provide water i.e. for general purpose.
Increased generation of waste
• Adopt waste minimization at source.
• Monitoring the fate of disposed wastes to ensure they are legally land filled at a recognized controlled site.
• Adhering to waste management regulations of 2006.
The full report of the proposed project is available for inspection during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Foresty, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, Upper Hill, P.O. Box 30126–00200, Nairobi
(b) Director General, NEMA, Popo Road, off Mombasa Road, P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Nairobi City County.
A copy of the EIA report can be downloaded at www.nema.go.ke
The National Environmental Management Authority, invites members of the public to submit oral or written comments within thirty (30) days from the date of publication of this notice to the
Director General, NEMA to assist the Authority in the decision making process for this project.
Comments can also be e-mailed to dgnema@nema.go.ke
MAMO B. MAMO, Director-General, MR/7803200 National Environment Management Authority.
Dated the 29th August, 2025.
MAMO B. MAMO,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
12192
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 29th August 2025