GAZETTE NOTICE NO. 13539
GAZETTE NOTICE NO. 13539
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
APPOINTMENT
PURSUANT to section 59 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received
an Environmental Impact Assessment Study Report for the above-
proposed project.
The proponent, Lesonia Residency Limited, proposes to construct
a 16-storey residential building with 3No. Basements, ground floor, 1st
floor and typical 2nd to 16th floor comprising a total of 278No.
residential apartments (154No. one-bedroom units, 93No. two-
bedroom units and 31No. three-bedroom units), 232 parking bays,
children play area, gym, swimming pool, 2 yoga studios, 2 steam
rooms, resident lounge, a management office and other associated
facilities and amenities on plot L.R. No. Nairobi/Block 23/380 located
along Gatundu road in Kileleshwa Area, Nairobi County.
The following are the anticipated impacts and proposed mitigation
measures:
Impact Mitigation Measures
Soil erosion • Obtain an excavation permit from
Nairobi City County before excavation
begins.
• Excavation will be undertaken using
standard equipment and no blasting of
the rocks will be carried out to avoid the
destruction of neighbouring
developments.
Water demand • Extend the connection of the main water
supply to the proposed development
upon acquisition of a connection permit
from NCWSC.
• Drill a borehole as an alternative source
of water during the project cycle.
• Harvest rainwater for reuse to
supplement the existing surface and
subsurface water sources.
• Monitor the water consumption within
the site every month.
Energy demand • Extend the connection of the proposed
development to the existing conventional
sewer system upon acquisition of a
connection permit from NCWSC.
• Install solar panels as an alternative
source of renewable energy for the
proposed development.
• Install a standby generator as a backup
source of energy for the development.
6370 6370
Impact Mitigation Measures
• Install energy-efficient fixtures and
fittings within the development such as
LED bulbs.
• Monitor the energy consumption within
the site every month.
Liquid waste • Extend the connection of the proposed
development to the existing conventional
sewer system upon acquisition of a
connection permit from NCWSC.
• Design and construct an internal
reticulation system which can
consistently handle the loads even at
peak volumes.
• Provide adequate sanitary conveniences
to the workers and ensure they are kept
clean.
Solid waste • Design and implement a three-year
Waste Management Plan.
• Provide a centralised Waste Collection
Centre with colour-coded receptacles for
solid waste management.
• Segregate non-hazardous waste into
organic and non-organic fractions before
final disposal.
• Engage a NEMA-licensed waste
transporter to collect and dispose of the
segregated waste to designated disposal
sites.
Traffic density • Ferry building materials and construction
waste during the off-peak hours.
• Engage traffic marshals to control traffic
in and out of the site.
• Install traffic control/warning signs to
inform the motorists and public of the
potential hazards.
• Provide temporary car parking spaces for
construction vehicles within the site
boundary.
Air pollution • Screen the entire site using dust
screens/nets to control and arrest
construction-related dust.
• Sprinkle water in the work areas twice
every day to prevent fugitive dust
violations.
• Ambient air quality monitoring within
the site.
Noise and excessive
vbrations
• Construction activities are to be
undertaken between (0800hrs to
1800hrs) on weekdays and (0800hrs to
1300hrs) on Saturdays only.
• Sensitize workers and drivers on
minimal permissible noise levels.
• Regular maintenance of the machinery to
reduce frictional noise.
• Ambient noise quality monitoring within
the site.
Security risks • Engage licensed security personnel to
safeguard the property and monitor the
movement of people in and out of the
site.
• Keep records of all construction workers
as per DOSHS requirements.
• Install CCTV cameras and security lights
at strategic points within the site to
monitor and enhance the security of the
Impact Mitigation Measures
property.
Health and safety of
workers
• Register the construction site as a
workplace with the DOSHS before the
construction begins.
• Provide adequate and appropriate PPE
and ensure that all workers wear them at
all times.
• Provide first aid facilities and ensure that
the workers are trained in emergency
response.
• Develop an Emergency Response Plan to
manage the occurrence of anticipated
hazards during the construction phase.
• Comply with the Occupational Safety
and Health Act (OSHA), 2007 and all
other relevant regulations governing the
health and safety of the workplace.
Loss of vegetation • Apply for a tree-cutting clearance
certificate from the Nairobi County
Director of Forestry before cutting down
the trees and adhere to the conditions.
• Undertake a comprehensive landscaping
exercise by planting indigenous trees and
grass within the open spaces.
Impacts Mitigation Measures
Noise generation • Schedule project activities between 8:00
a.m. and 5.00 p.m.
• Train operators on efficient operation
practices, including minimizing idling
time and hooting.
• Maintenance of equipment to ensure
optimal performance and reduced noise
emissions.
• Carry out periodic noise level
measurements at the site.
• Provide PPE to all personnel operating or
working above 85db.
• Install noise barriers, silencers, or
dampeners on machinery.
Gaseous emissions • Use covered containers for handling and
transporting waste oil.
• Regularly service machinery and
generators to reduce exhaust emissions.
• Monitor ambient air quality periodically
to detect pollutant levels.
• Avoid open burning of oily waste, rags,
or sludge.
• Minimize idling of vehicles and heavy
equipment within the facility.
Waste generation and
disposal
• Segregate waste at source.
• Provide designated waste bins for
different waste streams.
• Contract licensed waste handlers for
collection and disposal.
• Encourage reuse and recycling where
feasible
• Conduct periodic audits to monitor waste
management practices.
Injuries from working
at heights and in
Confined Spaces
• Conduct job-specific risk assessments.
• Develop and implement permit-to-work
19th September, 2025 THE KENYA GAZETTE
Impact Mitigation Measures
systems.
• Provide proper signage and barriers.
• Use full-body harnesses and fall arrest
systems.
• Ensure ladders and scaffolds are
inspected regularly.
• Ensure continuous ventilation of the
confined space.
Oil spillages • Conduct routine inspection and
monitoring of all oil and fuel storage
tanks.
• Maintenance of fully stocked spill kits at
the Yard
• Develop and implement a Spill
Prevention and Emergency Response
Plan (SPERP).
• Pave all oil handling and storage areas.
• Construct an oil-water interceptor in the
drainage system.
• Construct bund walls around the fuel tank
farm to contain potential spills or leaks.
• In case of accidental spillage.
• Immediately stop the source of the spill.
• Activate emergency response plan and
alert responsible personnel.
• Contain the spill using sand, absorbent
booms, or soil bunds.
• Block nearby drains to prevent oil from
entering water systems.
• Use spill kits to absorb and clean up
spilled oil.
Fire • Install fire extinguishers at key points
around the plant.
• Train all workers on fire safety, use of
extinguishers, and evacuation procedures.
• Conduct regular fire drills and emergency
preparedness exercises.
• Install smoke detectors and heat sensors
in critical areas.
• Prohibit open flames and smoking within
site.
• Clearly label flammable materials.
• Keep fire assembly points and access
routes well-marked and unobstructed.
Occupational health
and safety risks
• Construction of a site office for
coordinating activities.
• Appointment of a responsible
team/persons to oversee Health, Safety,
and Environment (HSE) matters
• Provision of Workers Injury Benefits Act
(WIBA) coverage for all site personnel
• Engagement of security services from a
reputable security firm at the
• Provision of clean drinking water,
adequate sanitation facilities, a first aid
kit, and other basic welfare amenities at
the site
• Maintenance of a register of workers
Impact Mitigation Measures
Environmental
Impacts
Mitigation Measures
Soil erosion • Obtain an excavation permit from
Nairobi City County before excavation
begins.
• Excavation will be undertaken using
standard equipment and no blasting of the
rocks will be carried out to avoid the
destruction of neighbouring
developments.
• Control excavation works especially
during rainy/wet conditions.
Noise and excessive
vibrations
• Construction activities are to be
undertaken between 0800hrs to
1800hrs on weekdays and 0800hrs to
1300hrs on Saturdays only.
• Sensitize workers and drivers on minimal
permissible noise levels.
• Regular maintenance of the machinery to
reduce frictional noise.
• Ambient noise quality monitoring within
the site.
Air pollution • Screen the entire site using dust
screens/nets to control and arrest
construction-related dust.
• Sprinkle water in the work areas twice
every day to prevent fugitive dust
violations.
• Ambient air quality monitoring within the
site.
Solid waste • Design and implement a three-year Waste
Management Plan.
• Provide a centralised Waste Collection
Centre (WCC) with colour-coded
receptacles for solid waste management.
• Segregate non-hazardous waste into
organic and non-organic fractions before
final disposal.
• Engage a NEMA-licensed waste
transporter to collect and dispose of
segregated waste to designated disposal
sites.
Liquid waste • Extend the connection of the proposed
development to the existing conventional
sewer system upon acquisition of a
connection permit from NCWSC.
• Design and construct an internal
reticulation system which can
consistently handle the loads even at peak
volumes.
• Provide adequate sanitary conveniences
to the workers and ensure they are kept
clean.
Storm water drainage • Construct internal drainage channels
covered with gratings for storm water
management.
• Install rainwater-harvesting facilities
within the site structures to reduce the
amount of storm reaching the surface.
Water demand • Extend the connection of the main water
supply to the proposed development upon
acquisition of a connection permit from
NCWSC.
• Drill a borehole as an alternative source
6372 6372
Impact Mitigation Measures
of water during the project cycle.
• Harvest rainwater for reuse to supplement
the existing surface and subsurface water
sources.
• Monitor the water consumption within
the site every month.
Energy demand • Install an onsite transformer to supply
energy to the proposed development
subject to the acquisition of a connection
permit from KPLC.
• Install solar panels as an alternative
source of renewable energy for the
proposed development.
• Install energy-efficient fixtures and
fittings within the development such as
LED bulbs.
• Monitor the energy consumption within
the site every month.
Traffic density • Ferry building materials and construction
waste during the off-peak hours.
• Engage traffic marshals to control traffic
in and out of the site.
• Install traffic control/warning signs to
inform the motorists and public of the
potential hazards.
• Provide temporary car parking spaces for
construction vehicles within the site
boundary.
Health and safety of
workers
• Register the construction site as a
workplace with the DOSHS before the
construction begins.
• Provide adequate and appropriate PPE
and ensure that all workers wear them at
all times.
• Provide first aid facilities and ensure that
the workers are trained in emergency
response.
• Develop an Emergency Response Plan
(ERP) to manage the occurrence of
anticipated hazards during the
construction phase.
• Comply with the Occupational Safety and
Health Act (OSHA), 2007 and all other
relevant regulations governing the health
and safety of the workplace.
Security risks • Engage licensed security personnel to
safeguard the property and monitor the
movement of people in and out of the site
• Keep records of all construction workers
as per DOSHS requirements.
• Install CCTV cameras and security lights
at strategic points within the site to
monitor and enhance the security of the
property.
The full report of the proposed project is available for inspection
during working hours at:
(a) Principal Secretary, Ministry of Environment, Climate
Change and Forestry, NHIF Building, 12th Floor, Ragati
Road, Upper Hill, P.O. Box 30126–00100, Nairobi.
(b) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(c) County Director of Environment, Nairobi City County.
A copy of the report can be downloaded at www.nema.go.ke
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process regarding this project.
Comments can also be emailed to dgnema@nema.go.ke
MAMO B. MAMO,
Director-General,
MR/7803766 National Environment and Management Authority.
Dated the 19th September, 2025.
MAMO B. MAMO,
Director-General, National Environment and Management Authority.
Extracted Entities (1)
previous_gazette_ref
13539
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Section
- section 59
- Signed By
- MAMO B. MAMO
- Title
- Director-General, National Environment and Management Authority
- Date Signed
- 19th September 2025
- Page
- 39
- Extraction Method
- regex
Source Gazette
Vol. CXXVII No. 195
Published 6th March 2025