Back
OTHER 100% confidence via regex

GAZETTE NOTICE NO. 5184

PURSUANT to Clause 2 of Part III of the Schedule of tariffs 2023, notice is given that all prices for electrical energy specified in Part II of the said Schedule will be liable to a foreign exchange fluctuation adjustment of plus 96.46 cents per kWh for all meter readings taken in April, 2023. Information used to calculate the forex adjustment 1796 1796 Parameter KenGen (FZ) KPLC (HZ) IPPs (IPPZ) TOTAL (FZ+HZ+IPPZ) Exchange Gain/(Loss) 256,302,778.53 207,737,958.46 194,554,576.57 658,595,313.56 Total units generated and purchased (G) excluding exports in March, 2023 1,128,085,140 kWh DANIEL K. BARGORIA, MR/4257629 Director-General.

Extracted Entities (1)

previous_gazette_ref

5184

Details

Signed By
DANIEL K. BARGORIA
Title
Director-General
Date Signed
20th April 2023
Page
23
Extraction Method
regex