GAZETTE NOTICE NO. 9134
GAZETTE NOTICE NO. 9134
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received
an Environmental Impact Assessment Study Report for the above
proposed project
The proponent, Habitat Heights Limited, is proposing to construct
a real estate residential development to cater for the medium and low
density residential living. The project will involve construction of
fourteen storeys, 30No. blocks comprising of 8,888 units of one bed-
roomed, two bed-roomed and three bed-bedroomed apartments on plot
L.R. No. 7815/10 within Lukenya area, Mavoko Consituency, in
Machakos County.
The following are the anticipated impacts and proposed mitigation
measures:
Impacts Proposed Mitigation Measures
Increased solid
waste generation
• Materials from excavation of the ground and
foundation works shall be reused for
earthworks and landscaping.
• Express condition shall be put in the contract
that before the contractor is issued with a
completion certificate; he will clear the site of
all debris and restore it to a state acceptable to
the supervising architect and environmental
consultant.
• Bins/receptacles shall be placed at strategic
locations within the site.
• The contractor and proponent shall work with
private refuse handlers and local council to
facilitate sound waste management.
• Wastes shall be properly segregated and
separated to encourage recycling of some
useful waste materials.
• Use of an integrated solid waste management
system through a hierarchy options.
Surface drainage • Drainage channels shall be installed in all
areas that generate or receive surface water.
• Drainage channels will be covered with metal
gratings or other suitably approved materials
to prevent occurrence of accidents and dirt
entry that may affect flow of run-off.
• Drainage channels will be designed with
regard to peak volumes.
• Paving of sidewalks, parking and other open
areas shall be done using pervious materials.
Site security • The management shall strategically install
lighting as well as security alarms and backup
systems including surveillance of the area on
a 24 hours basis.
• Security guards shall protect the property in a
24 hour basis and document any suspect
movement within the facility and its environs.
Air quality • Provision of full protective gear for workers.
• Regular cleaning or sprinkling of water to
suppress dust.
Public health • The contractor shall institute HIV/AIDS
awareness and prevention campaign amongst
his workers for the duration of the contract.
• The contactor shall provide sanitary facilities
on site for the workers.
Water use • Provision of notices and information signs
within the project site to notify on means and
need to conserve water.
• Installation of water conserving taps.
• Encouragement of water re-use/recycling.
Fire hazards • Installation of an automatic fire alarm system
for the entire facility.
27th September, 2019 THE KENYA GAZETTE
Impacts Proposed Mitigation Measures
• All fire control and fighting facilities shall be
installed following local council fire masters
requirements and approval.
• Firefighting equipment shall be strategically
positioned, regularly maintained and serviced.
Traffic control • The contractor shall erect clear road signs
showing speed limits and warning other
motorists of turning vehicles.
• The contractor will load the vehicles to within
the permissible loads.
• The contactor will arrange for bulk
transportation of his materials during off-peak
times.
Occupational
health and
safety
• Workmen shall be provided with suitable
protective gear.
• There will be a fully equipped first aid kits on
site.
• A safety officer who has a first aid training
and knowledge of safety procedures will be
provided on site.
• The contractor will provide insurance for the
workmen.
• The contractor will be required to adhere to
Factories and Other Places of Work Act.
The full report of the proposed project is available for inspection
during working hours at:
(a) Director–General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(b) Principal Secretary, Ministry of Environment and Forestry,
NHIF Building, Community, P.O. Box 30126–00100,
Nairobi.
(c) County Director of Environment, Machakos County.
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision making process of the plan.
GEOFFREY WAKHUNGU,
Director-General,
MR/6722370 National Environment Management Authority.
Dated the 27th September, 2019.
GEOFFREY WAKHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
9134
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAKHUNGU
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 27th September 2019