GAZETTE NOTICE NO. 11668
GAZETTE NOTICE NO. 11668
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
ESTABLISHMENT
Pursuant to Regulation 21 of the Environmental Management and
Co-ordination (Impact Assessment and Audit) Regulations, 2003, the
National Environment Management Authority (NEMA) has received
an Environmental Impact Assessment Study Report for the above
proposed project.
9th November, 2018 THE KENYA GAZETTE
The proponent, Northern Water Services Board, is proposing to
construct a dam embankment across the dry river bed, spillway, off-
take tower, fully equipped water treatment works, a 225m3 and 100m3
water tank and a management structure in place. The Lesepe Small
Dam is located on a dry valley about 13Km away from Baragoi Town.
The following are the anticipated impacts and proposed mitigation
measures.
Impact Mitigation Measures
Soil erosion • Protective structures should be used to avoid
small-scale landslides where soil erosion
potential is high eg. gabbions and stable
slopes.
Water resources
depletion
• Promoting an effective water resource
management program.
• Initiate afforestation and agro- forestry
program for soil and water conservation.
• Initiate community capacity building on
water management, sanitation, operation and
maintenance.
• Ensure that environmental flow requirements
are met by releasing steady.
Dust generation
• Enclosing demolition sites.
• Spraying water on dusty roads.
• Covering or enclosing transportation
vehicles, controlling the speed of vehicles,
and selecting transportation routes to
minimize impact on dust sensitive receivers.
• Covering or watering open spoil or storage
sites.
• Sensitive receivers.
• Minimizing on-site storage time of
construction materials.
Noise generation
• No construction using heavy machinery,
from 22:00 to 6:00 Hrs, near settlements and
boarding schools.
• Non-discretionary use of noisy machinery
within 50m of settlements and boarding
schools.
• Good maintenance and proper operation of
construction machinery to minimize noise
generation.
• Installation of temporary sound barriers if
necessary.
• Selection of transport routes for large
vehicles.
Soil and drainage
disturbance
• Avoid construction during heavy rains.
• Planting of conservation vegetation to
control erosion and sedimentation.
• The drainage facilities should be cleared
periodically so as to ensure water flow.
• Avoid hampering surface water drainage
and plan for curative measures after
construction.
Loss of flora and
fauna
• Temporarily-used land (eg. during surveys,
pipe laying, vehicle- maintenance areas) will
return to its original use upon completion of
works.
• Ensure no trees are removed, but if they are,
replanting of indigenous plants and trees
should be done.
• Ensure the required construction period and
area is as small as possible so as not to
interfere with the fauna breeding periods.
Impact Mitigation Measures
Degradation of air
quality by
vehicular
emissions
• Construction and equipment emissions to be
kept within reasonable limits by maintaining
equipment to manufacturer’s specifications.
• Contractors to be encouraged to use
unleaded petrol and low sulphur diesel for
all vehicles and equipment.
The full report of the proposed project is available for inspection
during working hours at:
(a) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(b) Principal Secretary, Ministry of Environment and Mineral
Resources, NHIF Building, Community, P.O. Box 30521,
Nairobi.
(c) County Director of Environment, Samburu County.
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process of the plan.
GEOFFREY WAHUNGU,
Director-General,
MR/5555266 National Environment Management Authority.
Dated the 9th November, 2018.
GEOFFREY WAHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
11668
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAHUNGU
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 9th November 2018