Back
REGULATION
100% confidence
via regex
GAZETTE NOTICE NO. 2695
GAZETTE NOTICE NO. 2695
THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
(No. 8 of 1999)
REGULATION
PURSUANT to regulation 21 of the Environmental Management
and Co-ordination (Impact Assessment and Audit) Regulations, 2003,
the National Environment Management Authority (NEMA) has
received an Environmental Impact Assessment Study Report for the
above proposed project.
The proponent, Kenya Electricity Transmission Company Limited,
is proposing to construct a 400kV transmission line from Rongai in
Nakuru County, through Bomet County, and terminate in Kilgoris
Town, Narok County. Detailed scope of work for the project is as
follows:
1. Transmission Line
Rongai—Kilgoris 400kV Overhead Power Line (155km)
2. Substations
(a) Bay Extension at 400kV Rongai Substation
(b) Bay Extension at 400kV Kilgoris Substation
The following are the anticipated impacts and proposed mitigation
measures:
Impacts Proposed Mitigation Measures
Noise and vibration • The contractor to adhere to the EMCA Noise
and Excessive Vibration Pollution Control
Regulation, 2009.
• Contractor to ensure that noise levels
emanating from machinery, vehicles and
noisy construction activities (e.g. excavation,
blasting) are kept at a minimum.
• Sensitize construction drivers to avoid
running of vehicle engines or hooting.
• Regular servicing of engines and machine
parts to reduce noise generation.
• Ensure that all generators and heavy duty
equipment are insulated or placed in
enclosures (containers) to minimize ambient
noise levels.
• Trees to be planted around the site to provide
some buffer against noise propagation.
• The noisy construction works will entirely be
planned to be during day time when most of
the neighbors will be at work.
Air pollution • Ensure strict enforcement of on-site speed
limit regulations.
• Avoid excavation works in extremely dry
weather.
• Sprinkle water on graded access routes when
necessary to reduce dust generation by
construction and vehicles.
• Stockpiles of earth should be
enclosed/covered/watered during dry or
windy conditions to reduce dust emissions.
• PPE to be provided to employees and ensure
proper and constant use.
• Sensitize truck drivers and machine operators
to switch off engines when not in use.
• Regular servicing of engines and machine
parts to reduce exhaust emission generation.
THE KENYA GAZETTE 29th March, 2018
854 854
Impacts Proposed Mitigation Measures
• Alternative non-fuel construction equipment
shall be used where feasible.
Increased solid
waste generation
• Use of an integrated solid waste management
system i.e. the 3 R’s: 1. Reduction at source
2. Reuse 3. Recycle.
• Accurate estimation of the dimensions and
quantities of materials required.
• Use of durable, long-lasting materials that
will not need to be replaced as often, thereby
reducing the amount of construction waste
generated over time.
• Provide facilities for proper handling and
storage of construction materials to reduce
the amount of waste caused by damage.
• Use building materials that have minimal or
no packaging to avoid the generation of
excessive packaging waste.
• Reuse packaging materials such as removed
wooden poles, cartons, cement bags, empty
metal and plastic containers to reduce waste
at site.
• Waste collection bins to be provided at
designated points on site.
• Dispose waste more responsibly by
contracting a registered waste handler who
will dispose the waste at designated sites or
landfills only and in accordance with the
existing laws.
• Strict adherence to Waste Management
Regulations, 2006.
Generation of
wastewater
• Provide means for handling sewage generated
at the construction site.
• Conduct regular checks for sewage pipe
blockages or damages since such vices can
lead to release of the effluent into the land and
water bodies.
• Monitor effluent quality regularly to ensure
that the stipulated discharge rules and
standards are not violated.
• Strict adherence to Water Quality Regulations,
2006.
Oil spills hazards • Install oil trapping equipment in areas where
there is a likelihood of oil spillage e.g. during
maintenance of vehicles.
• In case of an oil spill, immediate clean up
measures will be instituted.
• Storage and liquid impoundment areas for
fuels, raw and in-process material solvents,
wastes and finished products should be
designed with secondary containment to
prevent spills and the contamination of soil,
ground and surface water.
• A written substations response plan should be
prepared and retained on the site and the
workers should be trained to follow specific
procedures in the event of a spill.
• Collected used oils should be re-used,
disposed of appropriately by licensed waste
handlers, or be sold for reuse to licensed
firms.
Destruction of
existing
vegetation and
habitat
• Conduct selective clearing of vegetation on
the way-leave corridor. Avoid unnecessary
vegetation clearing; only tall trees that poses a
danger to the transmission line and vegetation
on the foot plinth of the tower to be removed.
• Ensure proper demarcation and delineation of
the project area to be affected by construction
works.
• Specify locations for trailers and equipment,
Impacts Proposed Mitigation Measures
and areas of the site which should be kept free
of traffic, equipment, and storage.
• Designate access routes and parking within
the site.
• With Assistant from community, KWS and
KFS, initiate a tree planting exercise.
• Design and implement an appropriate
landscaping programme for the substations
site.
• Ensure no worker engage in acts of poaching.
• Restrict construction to day time.
• Observe applicable protected areas
regulations.
• Bush clearing to be selective. Only tall trees
on the wayleave corridor or vegetation on the
footprints of the towers to be removed.
• Consult the local KFS and KWS officer for
advice on construction timings to avoid
disturbing wildlife.Support community
initiatives in tree planting.
Disturbance on
Mau Forest
Complex
• Within the Forest Complex KETRACO to
consider underground cabling or at a
minimum reducing the way-leave to 15m.
• The proponent (and the contractor) must
strictly adhere to the Forest Conservation and
Management Act, 2016 and the Wildlife
Conservation and Management Act, 2013.
Disturbance on
wildlife
• At the proponent’s cost engage KFS and KWS
rangers to guard workers against wildlife and
to protect wildlife from hunting and poaching.
• Ensure no worker engage in acts of hunting or
poaching.
• Restrict construction to day time.
• Observe applicable Protected Area
regulations.
Impacts on
workers’ and
community health
and safety
• Ensure strict compliance with the
Occupational Safety and Health Act (OSHA)
2007.
• Prohibit access by unauthorized personnel
into the construction site.
• Train all employees and regularly sensitize
them on safe working procedures.
• Periodic community sensitization of the
dangers posed by the project.
• Place warning signs where necessary.
• Provide necessary PPEs to workers.
• Erect a perimeter fence to enclose the
substations.
Soil erosion and
storm-water
runoff
• Surface runoff and roof water shall be
harvested and stored in tanks so that it can be
used for cleaning purposes.
• A storm water management plan that
minimizes impervious area infiltration by use
of recharge areas and use of detention and/or
retention with graduated outlet control
structure will be designed.
• Apply soil erosion control measures such as
levelling of the project site to reduce run-off
velocity and increase infiltration of storm
water into the soil.
• Ensure that construction vehicles are
29th March, 2018 THE KENYA GAZETTE
Impacts Proposed Mitigation Measures
restricted to use existing graded roads.
• Ensure that any compacted areas are ripped
to reduce run-off.
• Roof catchments will be used to collect the
storm water for some substations uses.
• Construction of water pans to collect storm
water for substations use, tree planting and
landscaping.
Visual and aesthetic
impacts
• Extensive public consultation during project
planning.
• Structures at the site should be designed in
such a way that they will improve the beauty
of the surroundings.
• Restore site area through backfilling,
landscaping and planting of trees, shrubs and
grass on the open spaces to re-introduce
visual barriers.
• Design and implement an appropriate
landscaping programme.
Increase in social
vices including
HIV/AIDS
• Periodic sensitization forums for employees
on ethics, morals; general good behavior and
the need for the project to co-exist with the
neighbors.
• Guidance and counselling on HIV/AIDS and
other STDs to employees.
• Provision of condoms.
• Contractor to have a strong policy on sexual
harassment and abuse of office guided by
proponent’s policy on the same.
Cultural heritage
and archaeological
finds
• Upon discovery of a heritage site or an
archaeological find, the construction site will
be stopped, the site if possible will be
restricted using tapes or local materials, and
relevant authorities including local
administration officers and the museums of
Kenya informed for further instructions.
Resettlement and
loss of use
• Conduct consultation meetings with Project
Affected Persons and ensure timely
compensation for loss of property and land
use. Ensure adherence to country legal
legislations and World Bank Safeguard
Policy 4.12 on Involuntary Resettlement.
The full report of the proposed project is available for inspection
during working hours at:
(a) Director-General, NEMA, Popo Road, off Mombasa Road,
P.O. Box 67839–00200, Nairobi.
(b) Principal Secretary, Ministry of Environment and Mineral
Resources, NHIF Building, Community, P.O. Box 30126–
00100, Nairobi.
(c) County Director of Environment, Nakuru County.
(d) County Director of Environment, Bomet County.
(e) County Director of Environment, Narok County
The National Environment Management Authority invites
members of the public to submit oral or written comments within
thirty (30) days from the date of publication of this notice to the
Director-General, NEMA, to assist the Authority in the decision
making process of the plan.
GEOFFREY WAHUNGU,
Director-General,
MR/4143190 National Environment Management Authority.
Dated the 29th March, 2018.
GEOFFREY WAHUNGU,
Director-General, National Environment Management Authority.
Extracted Entities (1)
previous_gazette_ref
2695
Details
- Act / Legislation
- THE ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT
- Reference
- No. 8 of 1999
- Signed By
- GEOFFREY WAHUNGU
- Title
- Director-General, National Environment Management Authority
- Date Signed
- 29th March 2018
- Page
- 29
- Extraction Method
- regex
Source Gazette
Vol. CXX No. 39
Published 6th February 2018